https://xbrl.org/2026/transition-plan#StandaloneDocument https://xbrl.org/2026/transition-plan#Scope1 https://xbrl.org/2026/transition-plan#MediumTerm https://xbrl.org/2026/transition-plan#Absolute iso4217:GHS xbrli:pure utr:t utr:tCO2e utr:tCO2e iso4217:GHS TRNMETALSMININGGH001 2025-01-01 2025-12-31 TRNMETALSMININGGH001 2026-01-01 2030-12-31 TRNMETALSMININGGH001 2025-01-01 2025-12-31 production-ore-processed gold TRNMETALSMININGGH001 2025-01-01 2025-12-31 transition-mm:OwnEnergyUse self-generated-renewables-own-use TRNMETALSMININGGH001 2025-01-01 2025-12-31 transition:GHG TGT-MM-01 TRNMETALSMININGGH001 2025-01-01 2025-12-31 transition:ConsolidatedGroup TRNMETALSMININGGH001 2025-01-01 2025-12-31 transition:Category1

Birim Valley Resources Ltd

Transition Plan

Gold mining and a managed path to lower emissions

2025

Cover image

Document Information

Entity Name
Birim Valley Resources Ltd
Entity Identifier
TRNMETALSMININGGH001
Entity Identifier Scheme
http://standards.iso.org/iso/17442
Report currency
GHS
Report period
2025-01-01 – 2025-12-31
Decimal separator
. (FULL STOP)
Report generated
2023-10-09 00:00:00 +0000

All disclosures are related to the reporting period above unless specified otherwise.

Introduction

This plan sets out how Birim Valley Resources will reduce the emissions intensity of its mining operations by 2033. It follows the Disclosure Framework. Birim Valley Resources Ltd is a fictional company and every figure in this report is synthetic.

Table of contents

  1. 0 Document and entity information
  2. 1 Foundations
  3. 2 Implementation Strategy
  4. 4.1, 4.2, 4.3 Metrics
  5. 4.1, 4.2, 4.3 Targets
  6. 4.3 GHG emissions and removals
  7. 5 Governance

0 Document and entity information ⮌

Birim Valley Resources Ltd
Name of reporting entity The name of the entity whose transition plan this is. The entity's machine-readable identity is carried by the report's entity identifier, not by this concept; this exists so a standalone transition plan is attributable on its face, and it must agree with the identifier.
Standalone document
Transition plan reporting location Where these transition plan disclosures sit: within the entity's general purpose financial reports, in a standalone document alongside them, or in a standalone document that the general purpose financial reports cross-refer to. A single-value extensible enumeration.
2026-05-12
Transition plan publication date The date this version of the transition plan was published.

1 Foundations ⮌

We will reduce Scope 1 emissions from 310,000 tCO2e to 217,000 tCO2e by 2033. Progress is 9.6%.

  1. Replace diesel generation with a solar and battery hybrid at the main mine.
  2. Raise on-site renewables, now 61.5% of self-generated electricity used on site.
  3. Report yearly.
Strategic Ambition The entity's overarching aims: its objectives and priorities for responding and contributing to the transition to a low-GHG, climate-resilient economy.
Up to the end of 2028, the period of our current business plan and budget.
Short-term definition How the entity defines short-term in the context of transition planning (DF 1.1.e). The Taskforce recommends short-term is defined as no longer than three years (DF footnote 24); an entity defining it as longer should explain why.
From 2029 to the end of 2035, the period covered by our life-of-mine plans.
Medium-term definition How the entity defines medium-term in the context of transition planning (DF 1.1.e).
Beyond 2035, up to the year of our long-term ambition.
Long-term definition How the entity defines long-term in the context of transition planning (DF 1.1.e).

We assume that grid supply in Ghana stays unreliable enough that diesel remains our back-up, that solar and battery costs keep falling, and that the fuel price does not fall far enough to remove the saving from replacing diesel.

Our plan depends on grid reliability and fuel supply: we depend on the national grid for connection of the hybrid plant and on fuel imports, and we identified these by reviewing each site's energy sources and testing the plan against a prolonged supply shortage.

Key assumptions and external factors Key assumptions made and the external factors on which the entity depends to achieve the Strategic Ambition (matters such as policy and regulation, the decarbonisation of the economy, technology, data, demand, levels of warming, the physical impacts of the changing climate, and the effectiveness and limits of adaptation), their implications for achieving it, the timeframes over which they are expected to occur, and whether and how they are reflected in the financial statements.

2 Implementation Strategy ⮌

We plan GHS 1.8 billion of capital expenditure for the transition plan over the five years 2026 to 2030, 21.0% of our planned capital expenditure over the same period, and GHS 38 million for research and development of climate solutions. We fund the plan from operating cash flow, with the solar and battery hybrid financed partly by an equipment supplier. We expect diesel savings to repay the investment within about six years; other effects on cash flow are not quantified because the gold price dominates our results.

Financial planning Effects of the transition plan on the entity's financial position, financial performance, cash flows and resourcing.
GH₵ 1,800,000,000
Planned capital expenditure for the transition plan Capital expenditure the entity plans in order to implement its transition plan, over the period of the fact (the planning horizon it states).
Reporting period: 2026-01-01 – 2030-12-31
21.00 %
Planned capital expenditure for the transition plan, as a share of total planned capital expenditure The planned capital expenditure for the transition plan as a proportion of all capital expenditure the entity plans over the same period.
Reporting period: 2026-01-01 – 2030-12-31
GH₵ 38,000,000
Planned investment in research and development for climate solutions Investment the entity plans in research and development for climate solutions as part of its transition plan, over the period of the fact.
Reporting period: 2026-01-01 – 2030-12-31

4.1, 4.2, 4.3 Metrics ⮌

By Material and Metric identifier

2025
gold / production-ore-processed
t
Metric description Ore processed at the group's gold mines
Metric value, governance, business and operational 6,400,000.00
Metric unit description, governance, business and operational Tonnes, dry basis

By Self-generated renewables destination and Metric identifier

2025
Own energy use / self-generated-renewables-own-use
%
Metric description Proportion of self-generated renewable electricity consumed on site
Metric value, percentage 61.50

4.1, 4.2, 4.3 Targets ⮌

By Target Category and Target Identifier

2025
GHG / TGT-MM-01
Target metric, description Absolute Scope 1 emissions from mining operations
Target objective

To cut absolute Scope 1 emissions from mining operations by 30%, from 310,000 tCO2e at 2025 to 217,000 tCO2e by 2033. It is a mitigation target on gross emissions, for which we do not claim 1.5C alignment.

Target scope, description

The mining operations we control, including the main gold mine and its processing plant, for Scope 1 only; Scope 2 and Scope 3 are reported but are outside the target.

GHG scopes covered by target Scope 1
Target period end date 2033-12-31
Time horizon Medium term
Target base period date 2025-12-31
Target milestone, description

Interim milestone: no more than 264,000 tCO2e by 2029, a 15% reduction from 2025, on a straight-line path to the 2033 target of 217,000 tCO2e.

Target type Absolute
Target base value, GHG 310,000 tCO2e
Performance against target, GHG 301,072 tCO2e
GHG emissions intensity per monetary unit 0.0080 tCO2e per GH₵
Percentage of target achieved 9.60 %
Target informed by the latest international climate agreement NO
International climate agreement, description The Paris Agreement informed our choice to set a target and its year, and we checked the target against the Nationally Determined Contribution of Ghana, but we do not claim that it is aligned to a 1.5C pathway: we judge a faster fall in emissions is not achievable while our mines depend on diesel haulage and unreliable grids.
Target validated by a third party YES
Target review process, description

The Board Sustainability Committee reviews progress quarterly and reviews the target itself once a year, when the annual report is approved. We re-baseline a target if acquisitions, disposals or changes in method move the base by more than 5%. The target and its methodology have been validated by a third party, the Science Based Targets initiative.

Performance trend, description

The measure stood at 301,072 tCO2e at the end of the period against 310,000 tCO2e at the base date, which is 9.6% of the way to the 2033 target. Progress came from the first phase of the solar and battery hybrid at the main mine.

Target value, GHG 217,000 tCO2e
Target progress monitoring metrics, description

We monitor Scope 1 and 2 emissions in tCO2e from fuel records and metered electricity at each site, diesel use per tonne moved, and the share of renewable electricity used on site, reported to the committee each quarter. Progress is expressed as the share of the way from the base to the target, which stands at 9.6%.

4.3 GHG emissions and removals ⮌

310,000 tCO2e
Absolute gross GHG emissions, Scope 1 Absolute gross Scope 1 GHG emissions generated during the reporting period, expressed as metric tonnes of CO2 equivalent. Measured in accordance with the Greenhouse Gas Protocol: A Corporate Accounting and Reporting Standard (2004) unless a jurisdictional authority or exchange requires a different method.
62,000 tCO2e
Absolute gross GHG emissions, Scope 2 Absolute gross Scope 2 GHG emissions generated during the reporting period, expressed as metric tonnes of CO2 equivalent. Where the location-based or market-based measurement basis is specifically required, use the separately named concepts instead.

We measure Scope 1, 2 and 3 emissions under the GHG Protocol Corporate Standard (2004) and its Scope 3 Standard, setting the boundary by operational control. All seven Kyoto gases are included and converted to CO2e using IPCC AR6 100-year global warming potentials. Fuel, explosives and electricity use are taken from site records and metering. Emission factors come from Ghana Energy Commission grid factors, fuel records and metered electricity at each site. We made no change to the approach in the reporting period.

GHG measurement approach, description The measurement approach, inputs and assumptions used to measure GHG emissions, the reason for choosing them, and any changes made during the reporting period with the reasons for those changes. It states the standard used: the GHG Protocol Corporate Standard (2004), or the method a jurisdictional authority or exchange requires instead (4.3.l.ii).

By Accounting Consolidation

2025
tCO2e
Consolidated accounting group
Absolute gross GHG emissions, Scope 1 310,000

By Scope 3 Category

2025
tCO2e
Scope 3 Category 1
Absolute gross GHG emissions, Scope 3 540,000

5 Governance ⮌

The Board Sustainability Committee oversees the transition plan. It approves the targets, meets quarterly to review progress against them, and reports to the full board, which considers climate when it approves strategy, major investments and risk appetite, including capital allocation between mines and the pace of run-down of our coal output. The committee weighs the trade-off between near-term returns and the targets, and takes independent advice on scenarios and on its own training needs.

Board oversight and reporting The governance body or bodies, or individual or individuals, responsible for oversight of the transition plan.

The Chief Executive is accountable to the Board Sustainability Committee for delivering the plan and chairs the Mine Energy Transition Group, which brings together Operations, Engineering, Procurement and Finance. Emissions and target data go through the same controls as our financial reporting, are reviewed by internal audit each year and are reported to the Board Sustainability Committee quarterly. Managers' climate objectives are part of their annual performance reviews.

Roles, responsibility and accountability Management's role in the governance processes, controls and procedures used to monitor, manage and oversee the transition plan.

7.0% of executive remuneration is linked to transition plan metrics, through a 13.0% weighting in the incentive plan. The measures are progress on Scope 1 emissions, the share of on-site renewable electricity and the replacement of diesel generation. The remuneration committee sets the measures each year and checks them against reviewed data before any award is made.

Incentives and remuneration How incentive and remuneration structures align with the Strategic Ambition.
13.00 %
Percentage weighting of transition plan metrics in the executive incentive plan The typical percentage weighting of the transition plan-related metric(s) within the incentive plan for the executive population (DF 5.4.a.iii).
7.00 %
Percentage of executive remuneration linked to transition plan metrics The percentage of total executive remuneration that is linked to transition plan-related metric(s) (DF 5.4.a.iv).